Commercial Kitchen

Here we are looking at a new commercial kitchen that started with a concrete substrate. Our company was contracted to provide a high quality seamless epoxy throughout their kitchen and service area. In this project, the owner wanted an aggressive floor finish for added slip resistance, so the optional high gloss epoxy seal coat was not installed. Once the project started (1350 combined sq/linear ft), it took two days to complete. The first day the floor prep and vertical epoxy base was installed, and the following day the floor was installed. The space was turned over to a satisfied owner on the third day. The quick installation of this flooring allowed other construction disciplines to come in and keep the overall construction project ahead of schedule for a grateful owner.